Here we cover the parts of the development plan appropriate to synthesis imaging. The goals of this development plan are to address pressing needs of the consortium partners and to push forward into new application areas. It is expected that this development plan will be revised from time to time to incorporate, for example, VLBI processing when appropriate.
Items in italics are not directly part of synthesis processing but are needed:
| Target | Duration | Due date | Who? |
| Initial version MeasurementSet DO | 1 week | March 97 | Cornwell |
| Non-Solvable ComponentSkyModel | 1 month | April 97 | Marson |
| CompositeSkyModel | 1 month | April 97 | Marson |
| Optimization of gain solutions | 1 month | April 97 | Wieringa |
| Optimization of gridding | 1 month | May 97 | Cornwell |
| GUI Interface to imager | 2 months | May 97 | Glendenning |
| Non-symmetric sampling of Fourier plane | 2 weeks | May 97 | Cornwell |
| Change imager to DO V2 | 1 month | June 97 | Cornwell |
| DSSImage | 1 month | June 97 | ? |
| Support of Complex Images | 1 month | June 97 | ? |
| Measures support in MS | 1 month | July 97 | Brouw |
| Formalization of calibration tables | 3 months | August 97 | Kemball |
| Simulation software | 2 months | July 97 | Marson |
| Disk-based FFTs | 2 months | June 97 | Brouw |
| Miscellaneous imager improvements | 1 month | June 97 | Cornwell |
| Mosaicing: imaging | 2 months | July 97 | Wieringa? |
| Image Projections | 1 months | August 97 | Brouw? |
| Full implementation of cross-calibration | 3 months | October 97 | Kemball |
| Wide-field imaging | 2 months | October 97 | Marson |
| Ionospheric Model | 1 month | October 97 | Noordam |
| Determination of instrumental parameters | 3 months | October 97 | ? |
| Visualization and editing of visibility data | 4 months | October 97 | Noordam |
| Testing of the ME on single dish data | 2 months | October 97 | ? |
| Fringe fitting and averaging | 2 months | October 97 | ? |
| Calibration of Tied arrays | 2 months | October 97 | Noordam |
| Freeze interfaces | 1 month | November 97 | Cornwell |
The main unknowns in the development plan are the impact of the beta release process, and of NRAO's commitment to OVLBI on the availability of personnel on the time scales described here.