Development plan

Here we cover the parts of the development plan appropriate to synthesis imaging. The goals of this development plan are to address pressing needs of the consortium partners and to push forward into new application areas. It is expected that this development plan will be revised from time to time to incorporate, for example, VLBI processing when appropriate.

Items in italics are not directly part of synthesis processing but are needed:

Target Duration Due date Who?
Initial version MeasurementSet DO 1 week March 97 Cornwell
Non-Solvable ComponentSkyModel 1 month April 97 Marson
CompositeSkyModel 1 month April 97 Marson
Optimization of gain solutions 1 month April 97 Wieringa
Optimization of gridding 1 month May 97 Cornwell
GUI Interface to imager 2 months May 97 Glendenning
Non-symmetric sampling of Fourier plane 2 weeks May 97 Cornwell
Change imager to DO V2 1 month June 97 Cornwell
DSSImage 1 month June 97 ?
Support of Complex Images 1 month June 97 ?
Measures support in MS 1 month July 97 Brouw
Formalization of calibration tables 3 months August 97 Kemball
Simulation software 2 months July 97 Marson
Disk-based FFTs 2 months June 97 Brouw
Miscellaneous imager improvements 1 month June 97 Cornwell
Mosaicing: imaging 2 months July 97 Wieringa?
Image Projections 1 months August 97 Brouw?
Full implementation of cross-calibration 3 months October 97 Kemball
Wide-field imaging 2 months October 97 Marson
Ionospheric Model 1 month October 97 Noordam
Determination of instrumental parameters 3 months October 97 ?
Visualization and editing of visibility data 4 months October 97 Noordam
Testing of the ME on single dish data 2 months October 97 ?
Fringe fitting and averaging 2 months October 97 ?
Calibration of Tied arrays 2 months October 97 Noordam
Freeze interfaces 1 month November 97 Cornwell

The main unknowns in the development plan are the impact of the beta release process, and of NRAO's commitment to OVLBI on the availability of personnel on the time scales described here.


next up previous contents home.gif
Up: NOTE 201 - UPDATED AIPS++ SYNTHESIS DEVELOPMENT PLAN Previous: Prerequisites   Contents
Please send questions or comments about AIPS++ to aips2-request@nrao.edu.
Copyright © 1995-2000 Associated Universities Inc., Washington, D.C.

Return to AIPS++ Home Page
2004-08-28