Scheduling

The phasing is not strict. Phase I and II can proceed concurrently. Phases II, IV can be interchanged. Phase V obviously must come last.

I'd estimate phases I-IV are several FTE-months of effort each. Phase V is probably substantially longer, maybe 6 months. Hence the entire effort is probably 18-24 FTE-months. Phase II should be done by someone familiar with OTF data, phase III requires a moderate but not sophisticated understanding of interferometry, and the other phases require someone with a deep understanding.


next up previous contents
Up: NOTE 219 - AIPS++ Mosaicing development plan Previous: Phase V: Advanced mosaicing tools   Contents
Please send questions or comments about AIPS++ to aips2-request@nrao.edu.
Copyright © 1995-2000 Associated Universities Inc., Washington, D.C.

Return to AIPS++ Home Page
2004-01-31