LOFAR Status Meeting :: 02 Dec 2009

Setting of the meeting

Instead of the LOFAR status meeting we provide a short status update through email. — Michiel Brentjens, Harm Munk, Antonis Polatidis

Status updates

LOFAR Roll-out status

The usual LOFAR roll-out status table is attached. Changes since last week:

  1. CS103 CEP connection up
  2. CS001 CEP connection up
  3. CS003 Validated

which brings the total number of validated stations to 10.

FIXME

LOFAR Radio Obervatory Status
General

Next week, the LOFAR PC will meet at ASTRON to review observation proposals.