==== Review meeting ==== | ==== Review meeting ==== | ||
- | * | + | Present: Reinoud Bokhorst, Henk Mulder, Hopko Meijering (Slack), Teun Grit. By email: Thomas Franzen on behalf of SOS |
+ | |||
+ | - Hopko: CEP4 cpu30 warning was disappeared after reboot | ||
+ | - Reinoud: Cobalt1 test script complained about kis001. Cobalt1 checks not complete. Communication could be better. Solution: Coordinator needs to ask again in Slack. | ||
+ | - Reinoud: CEP4 Slurm update went okay. We discovered that Docker containers had also an old version of the Slurm client. We solved it by mounting the client from outside. | ||
+ | - Teun: A new script is discovering all CEP3 users of the past 2 months and picks up the email addresses from NIS. This script must be used to warn CEP3 users a week ahead about the upcoming stop-days. It can also be used to inform those users when the stop-day finishes. The script '' | ||
+ | - Reinoud: Some supervisor daemons were not stopped by Software Support. | ||
+ | - Teun: It would be good to have a IB status check in Zabbix for Cobalt2 | ||
+ | - (Next from the email by Thomas) | ||
+ | - All items on the SOS checklist were completed except for 'Check data recorded on DRAGNET' | ||
+ | - In the future, the stop day coordinator should be formally informed when SOS has completed the checklist. An e-mail should be sent by SOS to the stop day coordinator, | ||
+ | - The SLURM version mismatch was not detected during the stop day because 'test pre-processing pipeline’ was not on the SOS stop day checklist. This has now been added to the checklist. | ||
+ | - My understanding is that ROAdmin will keep a CEP3 users e-mail list up-to-date. They will inform the CEP3 users when the system will be unavailable during stop days and software roll-outs, and also when the system is back online again. Let me know if I have misunderstood this. Comment by Teun: It is the responsibility of the stop-day coordinator that the CEP3 users are well informed. He will create the list of email addresses and send it to the SOS person on duty for that stop-day and this SOS person will send the email out (cc to coordinator). The coordinator verifies this. |