public:stopdayactivities_24sep2019

Differences

This shows you the differences between two versions of the page.

Link to this comparison view

Both sides previous revision Previous revision
Next revision
Previous revision
Last revisionBoth sides next revision
public:stopdayactivities_24sep2019 [2019-09-19 08:14] – [Stop-day activities September 24-25, 2019] Jasmin Klipicpublic:stopdayactivities_24sep2019 [2019-09-24 06:45] – [Stop-day activities September 24-25, 2019] Richard Blaauw
Line 2: Line 2:
  
 ^Coordinator|Jasmin Klipic|klipic@astron.nl| ^Coordinator|Jasmin Klipic|klipic@astron.nl|
-^Software Support|Mattia Mancini|mancini@astron.nl|+^Software Support|Arno Schoenmakers|schoenmakers@astron.nl|
 ^Science, Operations and Support|Bernard Asabere|asabere@astron.nl| ^Science, Operations and Support|Bernard Asabere|asabere@astron.nl|
-^Observer|Henk Mulder|observer@astron.nl|+^Observer|Richard Blaauw|observer@astron.nl|
  
 ⇒ [[:engineering:stop_day_procedures|Description of stopday procedures]]\\ ⇒ [[:engineering:stop_day_procedures|Description of stopday procedures]]\\
Line 15: Line 15:
  
 ====   ==== ====   ====
- 
  
 ==== Cobalt2 ==== ==== Cobalt2 ====
Line 21: Line 20:
   * Reboots (ROadmin)   * Reboots (ROadmin)
   * restart IB Switch   * restart IB Switch
 +  * recabling 10G interfaces (Arjen K (vlans??)JDM)
  
  
Line 30: Line 30:
 ==== CEP4 ==== ==== CEP4 ====
  
-  * Reboots +  * reconfigure SLURM (jasmin) 
-  * restart IB Switches+  * Reboots (jasmin) 
 +  * restart IB Switches (skipped) 
  
 ==== LEXARS ==== ==== LEXARS ====
Line 39: Line 41:
 ==== LCU ==== ==== LCU ====
  
-  * Upgrade to CentOS 7.6 (Jasmin)+  * Upgrade to CentOS 7.6 (Jasmin) wait for confirmation
   * reboot (Jasmin)   * reboot (Jasmin)
 +
  
 ==== Portals ==== ==== Portals ====
Line 50: Line 53:
   * OS upgrade and reboot (Teun)   * OS upgrade and reboot (Teun)
   * Switch-over ldb003 / lcs119 (dbsrv1)   * Switch-over ldb003 / lcs119 (dbsrv1)
- 
  
 ==== LTA ==== ==== LTA ====
Line 60: Line 62:
   * None   * None
  
-==== Core switches ====+==== Core switches & network ==== 
 + 
 +  * Warm reset PD0. RD0, RD1 (Arjen K 3 p.m) 
 +  * SutfNet7 to 8 migration (LOFAR internet connection).
  
-  * Warm reset PD0. RD0, RD1 
  
 ==== DWG Lofar Systems ==== ==== DWG Lofar Systems ====
Line 103: Line 107:
  
 ====   ==== ====   ====
 +
 +\\
  
  
  • Last modified: 2019-09-25 08:02
  • by Reinoud Bokhorst