Stop-day activities October 2-3, 2018
Coordinator | Jasmin Klipic | roadmin@astron.nl |
---|---|---|
Software Support | Adriaan Renting | softwaresupport@astron.nl |
Science, Operations and Support | Pietro Zucca | sos@astron.nl |
Observer | Henk Mulder | observer@astron.nl |
⇒ Description of stopday procedures
⇒ LOFAR Schedule cycle 10
⇒ The next stopdays are scheduled for December 4-5.
Systems
Cobalt
- ✔ Reboots and idrac reboots. (Hopko)
CEP3
- ✔ Block access at 08:00 (Teun)
- ✔ Replace/reseat 7 broken disks (Kees)
- ✔ All nodes: file system check and reboot. (Kees)
CEP4
- Lustre upgrade (Hopko/Robin/Reinoud)
Increase /tmp to 4GB and tmpfs- CEP4 /tmp to tmpfs (will not be done) since can have impact to SLURM (will be discussed/planned for next STOP Day)
LEXARS
- No action. (need to be checked maybe will be upgraded to 7.5?)
LCU
- ✔ No reboots
Portals
- Mark text as ToDoUpdate & reboot using Spacewalk
Central Services lcs020 .. lcs030
- ✔ OS upgrade and reboot
- ✔ lcs022/027/030/031 will be switched off (need confirmation from Jens K, and Teun)
Other Central Services
- ✔ OS upgrade and reboot
LTA
- ✔ None
Aartfaac
- None
Core switches
- None
Software updates
MoM and related
- none
MAC/SAS
- none
CEP3
- Activate disk quota
- Check that software environment is the same on all nodes (lof015 included)
LCU
- None
CEP4
- Slurm update (cpu/gpu nodes tbd)
Aartfaac
- None
COBALT
- none
LTA
- none
In the field
DWG Lofar Systems
- update & reboot (if possible)
Review meeting
The minutes of the review meeting can be found here.