Stop-day activities March 3-4, 2020

CoordinatorJasmin Klipicroadmin@astron.nl
Software SupportMattia Mancini
Science, Operations and SupportBernard Asabere
ObserverJurjen J Slumanobserver@astron.nl

Description of stopday procedures
LOFAR Schedule cycle 15

  • Reboots (Hopko)
  • Restart IB Switch (Hopko)
  • Block access at 08:00 (Jasmin)
  • Reboots (Kees)
  • Reboots (Hopko)
  • Restart IB Switches (Hopko)
  • Reboots (Hopko)

skipp

  • Update & reboot (Jasmin)
  • OS upgrade and reboot (Teun, Jasmin)
  • Update & reboot (Jasmin)
  • Check NFS mounts after NFS server reboot.
  • reboot (Arjen K)
  • :!: Northstar & MySQL & dop385 should NOT be updated and rebooted due to proposal deadline.
  • Update & reboot (All)
  • None
  • None
  • None
  • None
  • None
  • None
  • none
  • none


  • Last modified: 2020-12-17 09:42
  • by Jasmin Klipic