Stop-day activities September 24-25, 2019
Coordinator | Jasmin Klipic | klipic@astron.nl |
---|---|---|
Software Support | Arno Schoenmakers | schoenmakers@astron.nl |
Science, Operations and Support | Bernard Asabere | asabere@astron.nl |
Observer | Richard Blaauw | observer@astron.nl |
⇒ Description of stopday procedures
⇒ LOFAR Schedule cycle 12
Systems
Cobalt2
- ✔ Reboots (ROadmin)
- ✘ restart IB Switch
- ✔ recabling 10G interfaces (Arjen K (vlans??)JDM)
CEP3
- ✔ Block access at 08:00 (Reinoud)
- ✔ Reboots (Kees)
CEP4
- ✔ reconfigure SLURM (Reinoud)
- ✔ Reboots (Reinoud)
- ✘ restart IB Switches (skipped)
LEXARS
- ✔ Reboots
LCU
- ✔ Upgrade to CentOS 7.7 (Jasmin) wait for confirmation
- ✔ reboot (Jasmin)
Portals
- ✔ Update & reboot (Jasmin)
Central Services lcs020 .. lcs030
- ✔ OS upgrade and reboot (All)
- ✔ Switch-over ldb003 / lcs119 (dbsrv1) (Reinoud)
LTA
- ✔ Update & reboot (Reinoud)
Aartfaac
- None
Core switches & network
- ✔ Warm reset PD0. RD0, RD1 (Arjen K 3:15 p.m)
- ✔ SurfNet7 to 8 migration (LOFAR internet connection).
DWG Lofar Systems
- ✔ Update & Reboot (All)
Software updates
MoM and related
- None
MAC/SAS
- None
CEP3
- None
LCU
- None
CEP4
- None
Aartfaac
- None
COBALT
- none
LTA
- none