Stop-day activities Feb 7, 2017
Coordinated by Reinoud. Preferred end time 15:00.
The order of the stop-day will be Cobalt, CEP4, CEP3.
Software Support: Jan David
Systems
- Updates and reboots
Cobalt
- Reset idrac
- Reboot
CEP3
- Do a filesystem check on /data of lof001-022 (Done by Hopko)
- Reboots
- Phase-out ldb002. Change DNS alias.
- lexar003 add extra disk 2 x 4TB
CEP4
- nop
LCU
- Update GPS position from Ansible (Richard)
- swap /localhome and /data
- Replace and test CN001 new generation
Central Services
- √ Add lta-data disk to DRBD
- √ Move LTA VM to primary host
- Upgrade Java at lcs029 (#10266)
Software updates
MAC/SAS
- none
CEP3
- none
CEP4
- none
Aartaac
- none