Stop-day activities Nov 1, 2016
Coordinated by Teun. Prefered end time 15:00.
Systems
No-Break
All equipment in rack D1 will be put on no-break power. Involved machines:
1u ccu099 1u sas099 1u mcu099 1u lu ldb001 (powered off) 1u ldb002 1u 1u ldb003 1u lcs120 1u lcs121 1u lcs122 1u 8u lse021 (powered off) 8u lse024 8u lexar001 8u lexar002 1u lfe001
cep2
- Swap locus095 and locus080 physically (Done by Kees)
Cobalt
- Reset idrac
- Reboot
CEP3
- Do a filesystem check on /data of lof001-022 (Done by Robin)
- Reboots
CEP4
- ?
Software updates
MAC/SAS
- Take into production MCU002 (CentOS7)
- Take into production CCU002 (CentOS7)
CEP2
- none
CEP3
- none
CEP4
- none