public:lsm_new:2009:2009-12-09_lsm

LOFAR roll-out update (G. Heald)
  • new CEP connections for a couple of stations
  • team to install station electronics in Potsdam
  • all superterp stations validated!
  • position of station available through GoogleMaps → link to be placed at one of the LOFAR pages
Observatory status update (M. Brentjens)
  • entire super terp connected → pointing will be verified today
  • no know electric fences at this moment
  • CS030 RCU 78 HBA signal is very bad
  • list nodes are phased out
  • lifs nodes are phased out
  • network modification completed, still resolving fall-out
  • estimated life-time of observations approx. 4–6 weeks, given the growing size of data-sets
  • solved issues:
    • MAC/SAS instability
    • RSP command dropped
    • discrete jumps in HBA power and RMS (possibly related to bad RCU in CS030)
Wijnholds - Status HBA station calibration
  • three-level approach
    1. characterization of the tiles
    2. station level
    3. array calibration → selfcal at CEP
  • redundancy calibration
    • redundant baselines measure the same visibilities