public:stopdayactivities_20210511

Lofar Stop-day activities May 11-12, 2021

CoordinatorWalter Greenwoodroadmin@astron.nl
Software SupportMattia Mancinimancini@astron.nl
Science, Operations and SupportBernard Asabereasabere@astron.nl
Observer (May 11)Henk Mulderobserver@astron.nl
Observer (May 12)Henk Mulderobserver@astron.nl

Description of stopday procedures
LOFAR Schedule cycle 15

Stopday status sheet

  • Reboots (Hopko)
  • Restart IB Switch (Hopko)
  • Block access at 08:00 (Walter)
  • Reboots (Kees)
  • Reboots (Hopko)
  • Restart IB Switches (Hopko)
  • head01 <> head02 switch (head02 should become master) (Jasmin)

Reboots (Hopko)

None

  • Update & reboot (Walter)
  • OS upgrade and reboot (Teun)
  • Update & reboot (Walter)
  • Check NFS mounts after NFS server reboot. (Teun)
  • reboot (Arjen K) (skip)
  • Update & reboot (All)
  • Non CentOS 7 systems: dop225, dop227, dop228, dop344, dop803 (Walter)
  • :!: Don't touch: dop411, dop462
  • None
  • None
  • None
  • None
  • None
  • None
  • none
  • none
  • Dell BIOS/UEFI updates (dsu tool)
  • Last modified: 2021-05-11 13:33
  • by greenwood